Rincian Progress Mingguan

 

Rumus Bobot Projeto 
= Jumlah (Rp)  Unidade do Projeto cada item  / Total Preco  Projeto la inclui taxa
= 288 m / 2,880.000
= G10/H10
======================
Minggu Lalu

Qty
= Qty 0 tamba sidauk iha atvidade

Progress Minggu Lalu
= Qty Minggu lalu / Kuantitas  projeto cada item
= J10/D10 

Bobot Minggu lalu 
=Progresso minggu lalu X bobot projeto cada item
= K10*I10 
= 0% * 0.805%

============

Progresso Minggu ini
= Qty Minggu ini / Kuantitas Projeto cada Item 
= M10/D10
= 288/288 m2 

Bobot Minggu ini 
=Progress Minggu ini  X bobot projto cada item
= N10* I10 
= 100% *0.805%

==================
Progresso

Qty Progresso
= Qty Minggu ini + Qty Minggu lalu 
= M10+J10 
= 288+0

Progress Progresso
= Qty Progress/ Qty Projeto cada item
= P10/D10
= 288/288 m2 

Bobot Progresso
=Progresso Progress* Bobot Projetu cada item 
= Q10*I10
= 100%* 0.805%

Comments