Rincian Progress Mingguan
Rumus Bobot Projeto = Jumlah (Rp) Unidade do Projeto cada item / Total Preco Projeto la inclui taxa = 288 m / 2,880.000 = G10/H10 ====================== Minggu Lalu Qty = Qty 0 tamba sidauk iha atvidade Progress Minggu Lalu = Qty Minggu lalu / Kuantitas projeto cada item = J10/D10 Bobot Minggu lalu =Progresso minggu lalu X bobot projeto cada item = K10*I10 = 0% * 0.805% ============ Progresso Minggu ini = Qty Minggu ini / Kuantitas Projeto cada Item = M10/D10 = 288/288 m2 Bobot Minggu ini =Progress Minggu ini X bobot projto cada item = N10* I10 = 100% *0.805% ================== Progresso Qty Progresso = Qty Minggu ini + Qty Minggu lalu = M10+J10 = 288+0 Progress Progresso = Qty Progress/ Qty Projeto cada item = P10/D10 = 288/288 m2 Bobot Progresso =Progresso Progress* Bobot Projetu cada item = Q10*I10 = 100%* 0.805%